Corporate Actions
Vikran Engineering bags LoAs worth Rs 530.80 crore from

04-Apr-26   16:12 Hrs IST

Vikran Engineering said that it has secured Rs 530.80 crore worth of distribution infrastructure orders from Maharashtra State Electricity Distribution Company (MSEDCL), a Government of Maharashtra undertaking.

These contracts are for undertaking distribution infrastructure strengthening works in the Nashik and Kolhapur zones under the ADB-funded power distribution enhancement program.

The Nashik package is valued at Rs 235.63 crore, while the Kolhapur package stands at Rs 295.17 crore.

The scope includes end-to-end EPC execution covering survey, design, engineering, supply, installation and commissioning of distribution infrastructure, including new substations, transmission lines, transformer augmentation, underground cabling and GIS-based asset mapping.

Both projects are to be executed on a turnkey basis with a completion timeline of 21 months from the respective award dates.

Rakesh Markhedkar, chairman and managing director, Vikran Engineering, said: These two LoAs from MSEDCL under the ADB-funded program are a strong validation of our technical capabilities and our consistent execution track record in large-scale power distribution infrastructure.

Winning both the Nashik and Kolhapur Zone packages through competitive national bidding is a clear vote of confidence in our engineering depth and project management capabilities.

Vikran Engineering provides end-to-end services from conceptualization, design, supply, installation, testing, and commissioning on a turnkey basis and has a presence across multiple sectors, including power, water, and railway infrastructure.

The company had reported a 37.9% decline in standalone net profit to Rs 20.91 crore on a 0.5% rise in net sales to Rs 266.46 crore in Q3 FY26 as compared with Q3 FY25.

The scrip had lost 0.34% to end at Rs 55.38 on the BSE yesterday.

Attention Investors: Stock Brokers can accept securities as margin from clients only by way of pledge in the depository system w.e.f. September 1, 2020. || Update your mobile number & email Id with your stock broker/depository participant and receive OTP directly from depository on your email id and/or mobile number to create pledge. || Pay 20% upfront margin of the transaction value to trade in cash market segment. || Investors may please refer to the Exchange's Frequently Asked Questions (FAQs) issued vide circular reference NSE/INSP/45191 dated July 31, 2020 and NSE/INSP/45534 dated August 31, 2020 and other guidelines issued from time to time in this regard. || Check your Securities /MF/ Bonds in the consolidated account statement issued by NSDL/CDSL every month.|| KYC is one time exercise while dealing in securities markets - once KYC is done through a SEBI registered intermediary (broker, DP, Mutual Fund etc.), you need not undergo the same process again when you approach another intermediary.|| No need to issue cheques by investors while subscribing to IPO. Just write the bank account number and sign in the application form to authorise your bank to make payment in case of allotment. No worries for refund as the money remains in investor's account.